Downtown Groveland/BOF Water System Improvements

Estimated project cost - $6 million

Estimated project start year - 2020

The Project involves installing or replacing approximately 10,203 linear feet of 8-inch diameter
water main as well as new gate valves, pressure reducing valves, and four fire hydrants in the
downtown Groveland water distribution system; approximately 10,306 linear feet of 8-inch
diameter water main as well as new gate valves, pressure reducing valves, and nine fire
hydrants in the Big Oak Flat water distribution system; approximately 7,212 linear feet of 8-inch
water main and two fire hydrants in the connection between the communities of Groveland and
Big Oak Flat; and approximately 1,956 linear feet of 8-inch water main and one fire hydrant in
the water distribution system that feeds White Gulch.


Specifically, the Project is broken down as follows:
Anticipated improvements to the downtown Groveland water distribution system:
• Construct 4,995 linear feet (LF) of 6” water main on the lots to the north of Highway
120.
• Construct 160 LF of 6” water main to connect the existing water main to the new
water main north of Highway 120.
• Construct 2,610 LF of 6” water main on the lots to the south of Highway 120 and
along Back Street.
• Construct 1,310 LF of 6” water main along Foote Street and extending to the east.
• Construct 2 segments of water main, 440 LF and 290 LF respectively, connecting the
new water main south of Highway 120 to the new water main along Foote Street.
• Construct 215 LF of 6” water main along Power House Street connecting the new
water main on Back Street to the new water main along Foote Street.
• Construct 385 LF of 6” water main connecting the new water mains north of
Highway 120 to the new water mains south of Highway 120.
• Construction of new gate valves, pressure reducing valves and fire hydrants along
the new water mains, as needed.
 

Anticipated improvements to the Big Oak Flat water distribution system:
• Replace 2,000 LF of 4” water main with 6” water main along Wards Ferry Road,
including two (2) gate valves and three (3) fire hydrants.
• Replace 1,015 LF of 4” water main with 6” water main along Scofield Street
including one (1) gate valve and three (3) fire hydrants.
• Replace 1,040 LF of 4” water main with 6” water main along Big Oak Road including
one (1) gate valve and one (1) fire hydrant.
• Replace 320 LF of 4” water main with 6” water main along Henderson Street
including one (1) gate valve and one (1) fire hydrant.
• Replace 295 LF of 4” water main with 6” water main along Black Road including one
(1) gate valve and two (2) fire hydrants.
• Replace 745 LF of 4” water main with 6” water main along Harper Street.

• Replace 250 LF of 4” water main with 6” water main along School Street including
two (2) gate valves.
• Replace 1,150 LF of 4” water main with 6” water main along Yates Street including
one (1) gate valve and one (1) fire hydrant.
• Replace 305 LF of 4” water main with 6” water main along Vassar Street including
one (1) fire hydrant and a crossing underneath highway 120.
• Construct 1,200 LF of 6” pipe along Ward Ferry Road and Scofield Street to loop the
system including one (1) new PRV, three (3) new fire hydrants, and two (2) new gate
valves.

Anticipated improvements to the water distribution system in the White Gulch area:
• Replace 5,170 LF of 6” water main along White Gulch Road, near Highway 120.
• Replace 1,200 LF of 4” water main with 6” water main along Old Highway 120.
• Construction of new gate valves, pressure reducing valves and fire hydrants along
the new water mains, as needed.